  • RIVERS OTHER THAN GANGA & ITS TRIBUTRIES*

     

     

     

     

     

    (Rupees in Crores)

    YEAR OF LAUNCH

    :

    July 1995

    SCHEDULE OF COMPLETION 

    :

    December  2005

    COST SANCTIONED (till  3/10)

    :

    Rs. 2401.36

    FUND RELEASED (till  3/10)

    :

    Rs. 1525.58

    FUND UTILISED (till  3/10)

    (Including State Share)

    :

    Rs. 1933.55

    FINANCIAL PROGRESS (%)

    :

    81.72 %

    NO. OF SCHEMES SANCTIONED

    :

    385

    NO. OF SCHEMES COMPLETED

    :

    271

    STATES COVERED

    :

    14                                                                                                      

    TOWNS COVERED

    :

    70

    RIVERS COVERED

    :

    31

     

     

    JBIC FUNDED PROJECT

    STP CAPACITY SANCTIONED

    :

    2621 mld

    STP CAPACITY CREATED                            

    :

    2197 mld