  • GANGA ACTION PLAN PHASE-II (Main Stem) *

     

     

     

     

     

    (Rupees in Crores)

    YEAR OF LAUNCH

    :

    July  1995/Oct. 1996 (For W.B.)

    SCHEDULE OF COMPLETION

    :

    March 1999/Dec. 2001 (For W.B.)

    COST SANCTIONED (till  3/10)

    :

    Rs.  591.43

    FUND RELEASED (till  3/10)

    :

    Rs.  410.49

    FUND UTILISED (till  3/10)

     (Including State Share)

    :

    Rs.  430.57

    FINANCIAL PROGRESS (%)

    :

    72.80%

    NO. OF SCHEMES SANCTIONED

    :

    315

    NO. OF SCHEMES COMPLETED

    :

    257

    STATES COVERED

    :

    8                                                                                                          

    TOWNS COVERED

    :

    60

    RIVERS COVERED

    :

    3

    STP CAPACITY SANCTIONED

    :

    275.51 mld

    STP CAPACITY CREATED              

    :

    185.95 mld

    *à Includes  Mahananda River